On October 27, 2026, Congress passed Decree 24-2026 on a national urgency basis, in a single reading and with the favorable vote of two-thirds of all members of Congress. The law creates a special, temporary framework to implement a passenger rail system in the metropolitan area of the Republic of Guatemala, from initial planning through commissioning and handover.
1. FEGUA will lead project execution.
The law designates Empresa Ferrocarriles de Guatemala (“FEGUA”) as the executing entity and tasks it with carrying out every stage of the project, including planning, structuring, design, construction, supervision, systems integration, testing and commissioning. To do so, FEGUA must coordinate with the Ministry of Public Finance, SEGEPLAN, the municipalities and the other competent public entities, which will be required to cooperate within the scope of their respective powers.
FEGUA may directly hire a specialized international firm or consortium to set up the Project Technical Management Office (“OGTP”). The OGTP will provide technical assistance and support to strengthen FEGUA’s capabilities, prepare procurements, manage contracts and execute the project. Its recommendations and reports will serve as the main technical input for FEGUA’s decisions and must be added in writing to the file of each procurement. The firm or consortium that makes up the OGTP may not participate in the project as a bidder, contractor or subcontractor, nor be a direct or indirect beneficiary of it.
2. Special procurement regime.
The procurement of works, goods, equipment, technology and services required for the project is excluded from the procedures of the Government Procurement Law (Ley de Contrataciones del Estado). FEGUA may contract public or private, domestic or foreign entities through processes based on international standards and designed to allow for agile, traceable and transparent evaluations.
The procurement strategy will be proposed by the OGTP and approved by FEGUA. Among other matters, it must define the project delivery model, the types of contract and the stages and timelines of the process. As a reference, the law points to international models such as NEC (New Engineering Contract) contracts. The processes must observe the principles of competition, equal treatment, transparency, integrity, value for money, traceability, fraud prevention and accountability, as well as applicable Guatemalan law.
To implement this regime, Article 12 tasks FEGUA with issuing and approving, as of the decree’s entry into force, the regulations, manuals and other internal instruments needed for the procurement, management and execution processes. These must comply with the law, the international cooperation agreements applicable to the project and the OGTP’s proposals. The decree does not set a specific deadline for issuing them.
3. Budget and investment planning.
FEGUA must have budget funds available before signing any contract. If performance of a contract spans several fiscal years, FEGUA must schedule the corresponding appropriations through its completion. It must also include the resources needed to implement the decree in its draft annual budget.
The law requires the creation of a specific section within the National Public Investment System to apply an integrated pre-investment and investment model. The formulation, prefeasibility, feasibility and design phases may be consolidated to speed up the project, and costs and activity schedules may be updated progressively during the investment phase.
4. Transparency, oversight and matters still to be defined.
FEGUA must publish the project’s contractual instruments on its website. If they are written in another language, it must also publish their Spanish translation, except for documents subject to confidentiality under the exceptions provided for in the law. The Office of the Comptroller General and FEGUA’s internal audit unit will oversee the project, and FEGUA must submit semiannual reports to Congress.
The law authorizes FEGUA to accept clauses on international standards and practices, arbitration and submission to international jurisdiction. However, the future commercial operation of the system, fares, subsidies, regulation and maintenance must be defined through specific legal, regulatory and contractual instruments.
5. Entry into force.
The decree must be signed into law, promulgated and published. Under Article 15, it will enter into force eight days after its publication in the Official Gazette.